Friday, December 20, 2013

Week 38 - Drywall Ends. Catwalk Begin.

The crews have continued to make progress on the drywall - and should have it finished today.  They will begin with the mudding process next week.  The initial framework for the steel catwalk was installed.  The outriggers and stringer for the stairs will likely get installed over the next two weeks.  Below are some progress pictures of the drywall as well as the catwalk.










Friday, December 13, 2013

Week 37 - Drywall Starts Going Up

Now that we are completely roughed-in with the electrical and plumbing, the dry-walling begins.  The crews started with the ceilings and the apartment.  The walls of the main house still need to have all the UMB installed so that we get a shadow-line where the drywall meets the flooring.  Over the next two weeks the remaining drywall will be installed and finished to a level 5.  Below are initial pictures of the dry-wall - more to come over the next two weeks as it is completed.






Monday, December 9, 2013

Week 36 - Front Door

This week George visited the woodworkers, Midland Cabinet, that will be making the custom front door.  The door will be a solid core door veneered in both sides with the same redwood as the siding on the house.  Below are the architectural-drawings showing the details of the door as well as some photos of the redwood.






Week 35 - Plaster

As the exterior of the house gets finished up, one of the last remaining elements is the plaster for the lower garage and apartment.  Below are pictures of the initial work formwork as well as the coating of the first scatch-coat.  This coat needs to cure a few weeks and then the subcontractor will return to apply two more coats before finishing it up.