Week 9 - Trenches and Plumbing

This week marked the delivery and installation of our first structural steal beam, which supports the floor for the basement apartment.  We also began digging the trenches and laying the plumbing for the apartment.  Trenches were also dug so that PG&E hookups can be moved from the south wall to the north wall of the garage so that the south wall can be moved and aligned with the new concrete retaining wall and footing.