This was a big week at the house - we finally saw installation of the exterior stair beam and cantilevered cast concrete treads. While we love the way the stairs look now, we will indeed have railings also installed. We also saw installation of the finish plumbing - including our hotly anticipated master bathroom bathtub. While all the interior work was going on, the painters were also there painting the walls and ceilings. Lastly, the site concrete form-work was also removed to reveal the board formed concrete - and the site was was graded and prepared for the paver steps. Below are status pictures of the various items throughout the house and the site.

Sunday, March 23, 2014
Sunday, March 16, 2014
Week 51 - Rebar, Concrete and Marble
With the grading prepared in the front yard, the contractors prepared all the form-work, installed all the rebar, and poured the concrete to make up the front retaining wall along Roosevelt Way, the two planters along Park Hill and the front entry step and stoop. Below are pictures of the progress showing the rebar and some of the board formed concrete. The form-work will be removed this coming week and we will be able to see all the board formed concrete.
This week we also saw the delivery and installation of the marble counter tops in the kitchen and master bathroom. The marble is Calacatta Caldia and we purchased two bookended slabs that were cut to form the kitchen counter, island and master bathroom counter.
This week we also saw the delivery and installation of the marble counter tops in the kitchen and master bathroom. The marble is Calacatta Caldia and we purchased two bookended slabs that were cut to form the kitchen counter, island and master bathroom counter.
Saturday, March 8, 2014
Week 50 - Floors + Site Walls
With the floors installed throughout the house, the flooring installers started the finishing process. First the floors need to be sanded then two layers of lye are applied and fished with three layers of polyurethane. Below are some pictures of the initial sanding process.
Below are some photos of the site work beginning. The crew started to dig out and prepare for the formwork for the font stair landing, planters along Park Hill, and retaining wall along Roosevelt Way. Soon enough we have all the formwork up and prepared for concrete.
Below are some photos of the site work beginning. The crew started to dig out and prepare for the formwork for the font stair landing, planters along Park Hill, and retaining wall along Roosevelt Way. Soon enough we have all the formwork up and prepared for concrete.
Sunday, March 2, 2014
Week 49 - Front Door Installation
The door finally arrived! First it needed to be stained and then installed in the rough opening. Below are pictures of the staining process, the opening before install, and the final installed door.
Sunday, February 23, 2014
Week 48 - Apartment Kitchen + Laundry/Utility Room
While the crews continue with the flooring, tiles and finishes in the house, we assembled and installed the IKEA casework in the kitchen of the apartment and laundry/utility room of the main house.
Below are a series of progress shots showing the assembly and installation of the apartment kitchen.
Below are a series of progress shots showing the assembly and installation of the apartment kitchen.
Below are a series of progress shots showing the assembly and installation of the main house laundry/utility room.